PACE · June 2026

Company — Month at a Glance

Edit budgets ✎
Committed
$1,574,804
MTD Actual
$1,504,659
Left to Get
$70,145
Projected Pace
$1,504,659
below committed
New Daily Budget
$0
needed/day × 0 days left
Workdays
22/22
0 left

Departments

DepartmentCommittedMTDRemainingMTD Daily AvgNeed / DayPaceStatus
HVAC Service$254,875$207,677$47,198$9,440$0$207,677BEHIND
HVAC Install$730,972$679,650$51,322$30,893$0$679,650BEHIND
Plumbing Service$303,672$317,554-$13,882$14,434$0$317,554ON PACE
Plumbing Install$151,569$162,201-$10,632$7,373$0$162,201ON PACE
Electrical Service$79,696$101,009-$21,313$4,591$0$101,009ON PACE
Electrical Install$54,020$36,568$17,452$1,662$0$36,568BEHIND
TOTAL$1,574,804$1,504,659$70,145$1,504,659BEHIND

Opportunity Funnel — MTD (all workdays)

MetricHVACPlumbingElectrical
Opps Booked166254184
Opps Ran140212134
Flips61169
TGL's Ran412810

Every number here is computed live from the daily entries — no hand-linked cross-tab formulas, so it can't drift out of sync the way the workbook did.